Pirotex pyrolysis plant: delivery of two modules, with a capacity of 2.5 tons / day, in Labinsk, Krasnodar Territory
August 29, 2020
In August 2020, installation and commissioning of two Pyrotex pyrolysis units with a total capacity of 5 tons / day for feedstock was carried out at the facility. The equipment reached its design capacity and was put into operation.
The photo from the facility (see below) shows that two ovens of 2.5 tons per day are connected in a single line, which allows the use of pyrolysis gas from one oven to start the pyrolysis reaction in another oven, thereby saving more than 50% of liquid fuel used to heat the crucible.